10x10 Concrete Slab Cost

A 10 ft × 10 ft concrete slab is 100 square feet. At a standard 4-inch thickness it needs about 1.36 cubic yards of concrete (with 10 % waste) and costs roughly $600 – $1,300 installed with a plain broom finish.

Need different dimensions? Use the full Slab Cost Calculator for a custom estimate.

Material & Cost Breakdown

MetricValueNotes
Square footage100 sq ft10 ft × 10 ft
Thickness4 inStandard residential
Concrete volume1.23 yd³Before waste
Order volume (10% waste)1.36 yd³Ready-mix ordering target
80 lb bags needed62 bagsIncluding waste
60 lb bags needed82 bagsIncluding waste
Ready-mix material cost$177$224~$130–$165 per yard delivered
Installed cost (broom)$600$1,300$6–$13 per sq ft

* Installed cost assumes a standard broom finish, easy site access, and a prepared sub-base. Decorative finishes, tear-out, poor soil, or pump-truck access will move the price higher.

How We Calculated It

  • Area: 10 ft × 10 ft = 100 sq ft
  • Volume: 100 sq ft × (4 in ÷ 12) = 33.3 cu ft ÷ 27 = 1.23 yd³
  • With 10% waste: 1.23 × 1.10 = 1.36 yd³
  • Bags (80 lb): 1.36 × 27 ÷ 0.60 cu ft/bag ≈ 62 bags

FAQs

How much does a 10x10 concrete slab cost?

A 10x10 (100 sq ft) concrete slab costs roughly $600 to $1,300 installed with a broom finish in 2026. Decorative finishes, tear-out, and site prep can raise the price.

How many cubic yards for a 10x10 slab?

At 4 inches thick, a 10x10 slab needs about 1.23 cubic yards before waste and 1.36 yards after a 10% ordering allowance.

How many 80 lb bags for a 10x10 slab?

You would need about 62 bags of 80 lb concrete (including 10% waste). Above roughly one cubic yard, ready-mix is usually cheaper and easier than bags.

Planning Your 10x10 Pour

When preparing to pour a 10 ft × 10 ft concrete slab, proper planning is essential to keep your project on budget. The dimensions directly determine the total square footage, which in turn dictates the amount of labor, forming materials, and finishing time required.

The thickness is equally important. While 4 inches is standard for this type of slab, increasing the thickness by just one inch will significantly increase the total cubic yards of concrete needed. Always ensure your sub-base is properly compacted and leveled; an uneven base can lead to thick spots that consume more concrete than your initial estimate predicted. Lastly, ordering with a 10% waste margin is a standard industry practice to account for minor spills, uneven ground, and the small amount of concrete left inside the delivery truck.